/sprint-plan

Slash Command Source

Create a sprint plan for $ARGUMENTS with explicit capacity math, a carry-over check, and a definition-of-ready gate. The first token(s) of $ARGUMENTS are the sprint goal; a trailing number is treated as team capacity (story points or person-days). If no capacity is given, compute it in Phase 1 — never invent it.

Usage

/sprint-plan <goal> [capacity]
# e.g. /sprint-plan "Checkout v2 ready for beta" 34

Phase 1 — Capacity Math (do the arithmetic, show it)

  1. Raw capacity = team size × working days in sprint × focus factor (default 0.7; ask if unknown)
  2. Deductions — subtract, explicitly and line by line: holidays/PTO, on-call/support rotation, ceremonies (~10%), known interrupts
  3. Velocity cross-check — compare against the rolling average of the last 3 sprints' completed (not committed) points. If computed capacity exceeds trailing velocity by >15%, plan to trailing velocity and say so.

Output a small table: raw → deductions → net capacity → trailing velocity → planning number.

Phase 2 — Carry-Over Check (before adding anything new)

  1. List every item carried over from the last sprint (not Done at sprint close)
  2. Re-estimate remaining effort — never carry the original estimate
  3. Carry-over consumes capacity first; new scope only gets what is left
  4. If carry-over exceeds ~30% of capacity, flag it as a systemic over-commitment signal and recommend a smaller commitment this sprint, not a bigger push

Phase 3 — Definition-of-Ready Gate (per story)

A story may enter the committed scope only if all of these hold — otherwise it goes to "needs refinement", not the sprint:

  • User story has a clear actor, action, and outcome (INVEST-compliant)
  • Acceptance criteria written and testable
  • Estimated by the team (not by the planner alone)
  • Dependencies identified and either resolved or scheduled
  • Small enough to finish within the sprint (split if not)

Generate INVEST-checked stories from an epic with:

python3 product-team/agile-product-owner/skills/agile-product-owner/scripts/user_story_generator.py

Phase 4 — Output Structure

  • Sprint goal — one sentence; everything committed must serve it
  • Capacity table — from Phase 1
  • Carry-over — from Phase 2, listed first in committed scope
  • Committed scope — stories that passed the DoR gate, summing to ≤ planning number
  • Stretch scope — clearly separated; pulled only if committed scope finishes
  • Risks and dependencies — with named owners
  • DoR exceptions — empty if the gate was honored; otherwise justify each

Repo Assets (verified paths)

  • Skill: product-team/agile-product-owner/skills/agile-product-owner/SKILL.md
  • Sprint planning template: product-team/agile-product-owner/skills/agile-product-owner/assets/sprint_planning_template.md
  • Sprint planning guide: product-team/agile-product-owner/skills/agile-product-owner/references/sprint-planning-guide.md
  • Story generator: product-team/agile-product-owner/skills/agile-product-owner/scripts/user_story_generator.py
  • /sprint-health — mid-sprint health check
  • /user-story — single-story generation with INVEST checks